Skip to content

Case study, Construction

Principal Designer support on a live construction project

A main contractor needed a Principal Designer to manage design risk and meet the client's CDM 2015 duties before hazards reached site.

Services

  • CDM consultancy
  • Principal Designer
CDM 2015
duties demonstrably met
1
clean H&S file handed over

The challenge

Where things stood

A main contractor took on a project where design risk was not being managed and the client's CDM 2015 duties were not being met. Without a Principal Designer coordinating health and safety through the design phase, hazards were being carried into construction unchallenged, which meant avoidable risk on site and exposure for the client if anything went wrong.

What we did

Our approach

We took on the Principal Designer role and built health and safety into the project from the design stage. We coordinated the designers, made sure significant risks were designed out where possible and reduced where not and kept the client informed of their duties at each stage. We produced and maintained the pre-construction information and made sure it reached the Principal Contractor in a form they could actually use.

Throughout, we applied the hierarchy of control rather than defaulting to managing it on site, which is where cost and risk usually pile up.

The outcome

What it changed

The project completed with the client's CDM duties demonstrably met, significant risks designed out before they reached site and a clean health and safety file handed over at the end.

Dealing with something similar?

Tell us where things stand and we will tell you straight how we would approach it.

Prefer to write it down? Fill in the form and we will be in touch.

We will only use your details to respond to your enquiry.

Our Accreditations & Professional Memberships

IFE
IFSM
IOSH
OSHCR
FPA
IIRSM
UK Fire
ABBE
NEBOSH
PQS
CABE
NAHFO
IFPO
Fire Aware
Living Wage
NAFDI
ISRM
IIAI
ISO
NFRAR
CILT
Leadership
ProQual